|
AKZO NOBEL - Bayport
Nouryset Expansion
- $1.1 Million
H&M provided extensive design services for the de-bottlenecking
of the Polymer Chemical Nouryset Plant. Field verified and routed large
quantities of small-bore stainless steel piping. Drainage and spill
control was included in the scope of the design.
AKZO NOBEL -
Deer Park
TMI Pilot Plant
Projects - $500,000
Provided design, fabrication and installation for two proto-type skid
mounted laboratory pilot plants and one skid mounted TMI Reactor Scale-up
pilot plant project.
BASELL USA INC.
- Baytown
Potable Water
Upgrade - Phase II
Provided project management, engineering and cad service to develop
a Class "A" Package for the purpose of obtaining competitive
lump sum bids for construction of the Phase II upgrade of the potable
water system. The Class "A" Package consisted of bid documents
including the Invitation to Bid scope of work including but not limited
to scope definition, equipment specifications. PFDs, P&IDs, piping
isometrics, foundation design and layouts, electrical and instrumentation
specifications and design complete with applicable construction drawsings
is for construction. In addition the Client requested and was provided
a construciton estimate with grade qualification of +/- 10%.
BORDEN CHEMICAL
INCORPORATED
Catalyst Change-out
- $65,000
Provided supervision, labor equipment and material for an unscheduled
unit turnaround. Dismantled two reactors, removed the spent catalyst
for disposal. Charged the reactors with new catalyst and reassembled
the reactors. Additional work included installing new packing in a scrubber
along with several large bore stainless steel piping modifications.
EXXONMOBIL CHEMICAL
COMPANY - Baytown
PSV Documentation
Provided engineering and field technical verifiation to support
the service and sizing documentation of approximately 840 pressure relief
valves in the Baytown Polymer Center pilot plant complex.
GNI CHEMICALS
CORPORATION
Cytec - $1.2
Million
H&M provided all piping, structural, civil, electrical, and instrumentation
design for this project. Provided instrument and electrical equipment
specifications, cost estimates and purchase orders. Provided major structural
modifications and calculations for the expansion of the existing structure
to support large Rotary Drum Filter and associated equipment. Equipment
modifications and a new refrigeration unit were evaluated, selected
and engineered.
Sartomer - $1.4
Million
H&M provided piping, civil, instrument, electrical, tank modifications
and new tank design. Engineered extensive structural modifications to
existing structure to support new 150-ton tank on weigh cells. Provided
equipment modifications, specifications, and associated calculations.
Butyl Chloride
- $850,000
Provided piping, instrument and electrical design for the installation
of a Pellet Bed Reaction Tank in the existing tank farm. Provided extensive
piping modifications to the existing Reactor Area in the Unit.
Miscellaneous
Minor Capital Projects - $200,000
Provided field construction services on miscellaneous civil, structural
and piping projects ranging in costs from $5,000 to $35,000.
GOODYEAR
Centrifuge Upgrade
- $1.25 Million
Replaced existing centrifuge and feeder with new higher capacity units,
upgraded associated pumps, piping and instrumentation. Existing structure
and floor was modified to accommodate the new centrifuge and feeder.
V-332/V-333 Upgrade
- $400,000
Relocated a new and larger tank V-332, two new pumps and all associated
piping. Replaced existing tank, V-333 and reworked associated piping.
Vent Header System
- $1.5 Million
Increased the capacity of the existing vent system by adding a Collection
Header, K.O. Drum and Seal Tanks. In addition a new blower and burner
for the existing steam boiler were added. The tanks and blower were
located in an existing structure requiring extensive modifications at
each level. The new burner required all of the associated piping to
be reworked. New paving, foundations and steel framing for a new cover
over the entire boiler area was also added.
ICI AMERICAS
BP Expansion
- $5 Million
This project involved a grass roots design for two (2) 50 M3 tanks in
a new diked area complete with structural racks, platforms, sumps, and
tank truck loading and offloading facilities. The process piping configuration
was very complex and involved extensive steam/hot water-jacketed pipe.
H&M provided all the design, estimates and bid packages for this
project.
TEXAS MOLECULAR
LLC
Capital Products-
$1 Million
Provided Civil, Structural, and Piping Design for the installation of
a new Thermal Oxidizer, Boiler and Filtered Water System. Also provided
construction services for the installation of the piping, structural,
miscellaneous auxiliary equipment, instrumentation and electrical systems.
VOPAK INDUSTRIAL
SERVICES
Concrete Containment
Walls - $80,000
Provided engineering, design and construction to redesign and rework
existing concrete containment walls in the waste disposal area.
©
2002 H&M Group.
|